Code Reference
StructuralACI 318-19

Section 18.7.1/Special Moment Frame Beams

ACI 318-19 Section 18.7 covers the design and detailing requirements for beams in special moment frames resisting earthquake forces, including flexural reinforcement limits, confinement hoops, and strong-column weak-beam checks.

What this section requires

Beams in special moment frames must satisfy dimensional limits and detailed reinforcement requirements. Section 18.7.2 limits the beam width to at least 10 inches and the width-to-depth ratio to at least 0.3. The clear span must be at least 4 times the effective depth. Section 18.7.4 limits the positive moment strength at any section to at least one-half the negative moment strength at the face of the joint, and neither positive nor negative moment strength at any section may be less than one- quarter of the maximum moment strength at either face of the joint. Section 18.7.5 requires hoops (closed stirrups with seismic hooks) within 2h of the column face at both ends of the beam, spaced at the smallest of d/4, 6 inches, or 6 longitudinal bar diameters. Outside the hoop region, stirrups must be spaced no more than d/2. Section 18.7.6 requires the strong-column weak-beam check: the sum of column moment strengths at a joint must be at least 1.2 times the sum of beam moment strengths at the same joint.

Why this section exists

Special moment frames are designed to dissipate earthquake energy through controlled yielding of beam reinforcement near beam-column joints. The reinforcement limits and confinement requirements ensure beams yield in a ductile flexural mode rather than failing in brittle shear. The strong-column weak-beam requirement forces plastic hinges to form in beams rather than columns, preventing story-mechanism (soft-story) collapse. The hoop spacing limits in the plastic hinge zone confine the concrete core and prevent bar buckling during the large inelastic rotations expected in design-level earthquakes. These provisions apply in Seismic Design Categories D, E, and F where special moment frames per ASCE 7 Table 12.2-1 are required or selected.

What plan reviewers look for

Plan reviewers check beam sections and schedules for compliance with dimensional limits (10-inch minimum width, 0.3 width/depth ratio). They verify hoop sizes, spacing, and extent in the plastic hinge zone (2h from column face). They check that hoops have seismic hooks (135-degree bends with 6-diameter extensions) rather than standard 90-degree hooks. They verify the flexural reinforcement limits (positive moment at least half the negative at the joint face). They check the strong-column weak-beam calculation at each joint. For special shear walls, parallel detailing requirements apply. They verify lap splices are not located in the plastic hinge zone.

Common violations

Standard stirrups in plastic hinge zone
A special moment frame beam shows standard open stirrups (90- degree hooks) in the 2h region near the column faces. Section 18.7.5 requires hoops (closed ties with 135-degree seismic hooks) in this zone to confine the concrete during cyclic loading. Standard stirrups cannot develop the required confinement.
Lap splice in plastic hinge zone
Beam longitudinal bars are lap spliced within 2h of the column face. Section 18.7.5.1 prohibits lap splices within the plastic hinge zone because cyclic yielding and bar slip degrade the splice bond. Splices must be located near midspan and must be confined by hoops per Section 18.7.5.3.
Compliance tip
On beam details, clearly delineate the plastic hinge zone (2h from each column face) and show the hoop configuration with seismic hooks, size, and spacing. Dimension the beam width and depth. Show lap splice locations at midspan, not in the hinge zone. Include the strong-column weak-beam calculation at each joint in the structural calculations.
Callout automatically checks your drawings against ACI 318-19 and 43+ other building codes and standards. Each finding includes the exact section reference, severity rating, and suggested resolution.
Try it with 50 free credits

Related sections

12.8.1Seismic Base ShearASCE 7-2218.10.1Special Structural Walls (Shear Walls)ACI 318-1925.5.1Lap Splice RequirementsACI 318-19

Related articles

8 ACI 318 Errors That Get Structural Concrete Drawings Rejected