Code Reference
ElectricalNEC 2023

Section 705.12/Point of Connection for Interconnected Power Sources

NEC 705.12 covers supply-side and load-side connections for solar PV and battery storage including the 120% bus rule.

What this section requires

Interconnected power production sources (solar PV, battery storage, wind, generators) must connect to the premises wiring system using either a load-side connection (Section 705.12(B)) or a supply-side connection (Section 705.12(A)). Load-side connections are made at the service panelboard using dedicated circuit breakers; the sum of overcurrent device ratings on the bus must not exceed 120% of the bus rating (the "120% rule"). Supply-side connections are made between the utility meter and the service disconnect, bypassing the bus ampere limitation. Both methods require a disconnect, proper overcurrent protection, and labeling at the service equipment.

Why this section exists

When a solar inverter or battery system feeds power into a panelboard, the bus and conductors carry both utility current and inverter current. Without the 120% rule, the combined current could exceed the bus rating, causing overheating and fire. The supply-side connection avoids this limitation by connecting upstream of the panelboard bus but introduces different safety considerations (working on energized conductors between the meter and disconnect). Both methods have specific safety requirements to prevent backfeed hazards.

What plan reviewers look for

Plan reviewers check the one-line diagram for the point of connection. For load-side connections, they verify the 120% rule: the sum of the main breaker and the inverter breaker must not exceed 120% of the bus rating. For supply-side connections, they verify the location between the meter and service disconnect. They check for the required disconnect, overcurrent protection, and directory labeling at the service equipment.

Common violations

120% rule exceeded
A 200-amp panel with a 200-amp main breaker has a 40-amp solar breaker added (240 amps total). The 120% rule allows a maximum of 240 amps (200 x 1.2), but only if the solar breaker is at the opposite end of the bus from the main breaker. If the panel bus is rated at 200 amps, the maximum is 240 amps including the main.
Service directory not updated
A solar PV system is connected to the service but the directory at the service disconnect does not identify the PV system as an additional power source.
Compliance tip
Show the point of connection on the one-line diagram. For load-side connections, document the 120% rule calculation (bus rating x 1.2 vs. sum of all breakers). Place the inverter breaker at the opposite end of the bus from the main. Update the service directory to identify all power sources.
Callout automatically checks your drawings against NEC 2023 and 43+ other building codes and standards. Each finding includes the exact section reference, severity rating, and suggested resolution.
Try it with 50 free credits

Related sections

690.12Rapid Shutdown of PV SystemsNEC 2023625.40Electric Vehicle Charging EquipmentNEC 2023706.1Energy Storage SystemsNEC 2023